Catsfield
- Connection date
- 9 Nov 2037
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted 4 Aug 2025
Rother, reference RR/2024/1535/P · Source: REPD - Technology
- Storage
- Total capacity
- 240 MW
- Connected now
- 0 MW
- Still to connect
- 240 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Embedded
- Region
- England and Wales
- Project number
- PRO-004143
- In the register since
- September 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 1 May 2026 registerCustomer changed from Battery Asset Management Limited to MAS 001 Limited
- 19 Dec 2025 registerCustomer changed from MAS 001 Limited to Battery Asset Management Limited
- 29 Aug 2025 registerSubstation name updated in the register (from Ninfield 132kV/400kV to Ninfield GSP)
- 29 Jul 2025 registerCustomer changed from Battery Asset Management Limited to MAS 001 Limited
- 27 Feb 2024 registerConnection point changed from REVIEW - Ninfield 132kV/400kV to Ninfield 132kV/400kV
- 30 Jan 2024 registerConnection point changed from Ninfield 132kV/400kV to REVIEW - Ninfield 132kV/400kV
- 29 Sep 2023 registerAdded to the register
Also at Ninfield GSP
Substation view1 other project, 370 MW still to connect at this substation in total. 130 MW is due to connect here before this project’s connection date of 9 Nov 2037.