Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

Catsfield

MAS 001 Limited at Ninfield GSP

Connection date
9 Nov 2037
Gate
Not stated
Status
Scoping
Planning consent
Granted 4 Aug 2025
Rother, reference RR/2024/1535/P · Source: REPD
Technology
Storage
Total capacity
240 MW
Connected now
0 MW
Still to connect
240 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Embedded
Region
England and Wales
Project number
PRO-004143
In the register since
September 2023

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 1 May 2026 register
    Customer changed from Battery Asset Management Limited to MAS 001 Limited
  • 19 Dec 2025 register
    Customer changed from MAS 001 Limited to Battery Asset Management Limited
  • 29 Aug 2025 register
    Substation name updated in the register (from Ninfield 132kV/400kV to Ninfield GSP)
  • 29 Jul 2025 register
    Customer changed from Battery Asset Management Limited to MAS 001 Limited
  • 27 Feb 2024 register
    Connection point changed from REVIEW - Ninfield 132kV/400kV to Ninfield 132kV/400kV
  • 30 Jan 2024 register
    Connection point changed from Ninfield 132kV/400kV to REVIEW - Ninfield 132kV/400kV
  • 29 Sep 2023 register
    Added to the register

Also at Ninfield GSP

Substation view

1 other project, 370 MW still to connect at this substation in total. 130 MW is due to connect here before this project’s connection date of 9 Nov 2037.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning consent

The planning decision or stage for this project, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition, with the planning authority and its reference. QueueWatch matched the project to that record. NESO’s status can lag behind planning decisions, so the two may differ.