Noventum Cottered
NOVENTUM POWER SOLAR 5 LIMITED at West Anglia Connection Node D 400kV Substation
- Connection date
- 31 Oct 2034
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 210 MW
- Connected now
- 0 MW
- Still to connect
- 210 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004092
- In the register since
- January 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Mar 2026 registerMarked as Gate 1
- 27 Aug 2024 registerConnection point changed from Cottered 400kV Substation to West Anglia Connection Node D 400kV Substation
- 27 Aug 2024 registerConnection date moved from 31 Oct 2030 to 31 Oct 2034 (+48 months)
- 27 Feb 2024 registerTechnology changed from Demand, Solar to Storage, Solar
- 30 Jan 2024 registerAdded to the register
Also at West Anglia Connection Node D 400kV Substation
Substation view3 other projects, 1.6 GW still to connect at this substation in total. 600 MW is due to connect here before this project’s connection date of 31 Oct 2034.