- Connection date
- 30 Oct 2035
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 249 MW
- Connected now
- 0 MW
- Still to connect
- 249 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003993
- In the register since
- December 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerCustomer changed from Apatura Battery Ltd to Apatura Project 35 Ltd
- 31 Jan 2025 registerConnection point changed from Saltholme GSP to Wearside Connection Node C 400kV Substation
- 27 Sep 2024 registerConnection date moved from 31 Oct 2033 to 30 Oct 2035 (+24 months)
- 28 Jun 2024 registerCustomer changed from GPC Battery Ltd to Apatura Battery Ltd
- 29 Dec 2023 registerAdded to the register
Also at Wearside Connection Node C 400kV Substation
Substation viewNo other projects in the register at this connection point.