QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / North Scotland

Corriemoillie BESS

FIELD CORRIEMOILLIE LTD at Corriemoillie 132kV Substation

Connection date
30 Sep 2029
Gate
Gate 1
Status
Scoping
Planning consent
Application submitted 6 Feb 2025
Scottish Government (S36), reference ECU00005155 · Source: REPD
Technology
Storage
Total capacity
200 MW
Connected now
0 MW
Still to connect
200 MW
Transmission owner
SSEN Transmission (SHET)
Agreement type
Direct Connection
Region
North Scotland
Project number
PRO-003992
In the register since
November 2023

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 26 Jun 2026 register
    Marked as Gate 1
  • 28 Feb 2025 register
    Customer changed from Virmati Energy Ltd to FIELD CORRIEMOILLIE LTD
  • 24 Dec 2024 register
    Customer changed from FIELD GAIA LTD to VIRMATI ENERGY LTD
  • 31 May 2024 register
    Customer changed from VIRMATI ENERGY LTD to Field Gaia Ltd
  • 28 Nov 2023 register
    Added to the register

Also at Corriemoillie 132kV Substation

Substation view

1 other project, 200 MW still to connect at this substation in total.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning consent

The planning decision or stage for this project, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition, with the planning authority and its reference. QueueWatch matched the project to that record. NESO’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.