QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland

Hunterston Hydrogen

STATKRAFT HYDROGEN UK HOLDING LIMITED at Hunterston 400/132kV

Connection date
31 Oct 2033
Gate
Not stated
Status
Scoping
Technology
Hydrogen
Total capacity
5 MW
Connected now
0 MW
Still to connect
5 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-003957
In the register since
January 2025

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 28 Feb 2025 register
    Connection point changed from Hunterston PARC 400kV Collector substation to Hunterston 400/132kV
  • 28 Feb 2025 register
    Technology changed from Storage, Hydrogen to Hydrogen
  • 31 Jan 2025 register
    Added to the register

Also at Hunterston 400/132kV

Substation view

3 other projects, 325 MW still to connect at this substation in total. 70 MW is due to connect here before this project’s connection date of 31 Oct 2033.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO