Craiginmoddie Wind Farm
- Connection date
- 30 Sep 2031
- Gate
- Gate 1
- Status
- Scoping
- Planning consent
- Granted 5 Nov 2025
Scottish Government (S36), reference ECU00002196 · Source: REPD - Technology
- Onshore wind
- Total capacity
- 92.4 MW
- Connected now
- 0 MW
- Still to connect
- 92.4 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-003829
- In the register since
- March 2024
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 7 Apr 2026 registerMarked as Gate 1
- 27 Sep 2024 registerSubstation name updated in the register (from Maybole 132/33KV Substation to Maybole 132/33kV)
- 26 Mar 2024 registerAdded to the register
Also at Maybole 132/33kV
Substation view2 other projects, 92.4 MW still to connect at this substation in total.