GALILEO 06
- Connection date
- 31 Oct 2037
- Gate
- Not stated
- Status
- Scoping
- Technology
- Onshore wind
- Total capacity
- 175 MW
- Connected now
- 0 MW
- Still to connect
- 175 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Embedded
- Region
- England and Wales
- Project number
- PRO-003810
- In the register since
- March 2024
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 28 Feb 2025 registerConnection point changed from Proposed Ferryside GSP to Llandyfaelog 132kV Substation
- 26 Mar 2024 registerAdded to the register
Also at Llandyfaelog 132kV Substation
Substation view1 other project, 286 MW still to connect at this substation in total. 111 MW is due to connect here before this project’s connection date of 31 Oct 2037.