Lairdmannoch Energy Park
LAIRDMANNOCH ENERGY PARK LIMITED at Lairdmannoch Energy Park 132kV substation
- Connection date
- 28 Jun 2030
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Storage + Solar + Onshore wind
- Total capacity
- 100 MW
- Connected now
- 0 MW
- Still to connect
- 100 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-003781
- In the register since
- September 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Awaiting Consents
- 28 Mar 2025 registerCustomer changed from WIND 2 PROJECT 4 LIMITED to LAIRDMANNOCH ENERGY PARK LIMITED
- 27 Feb 2024 registerTechnology changed from Storage to Storage, Solar, Onshore wind
- 29 Sep 2023 registerAdded to the register
Also at Lairdmannoch Energy Park 132kV substation
Substation viewNo other projects in the register at this connection point.