QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Transmission / Projects / South Scotland

Elmya Dalry BESS & PV

ELMYA ENERGY UK 17 LIMITED at Dalry 400kV Substation

Connection date
25 Oct 2033 (0 MW)
Gate
Gate 1
Status
Scoping
Technology
Storage
Total capacity
800 MW
Connected now
800 MW
Still to connect
0 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-003735
Tracked since
10 Oct 2026

Change history

Every change to this project across 14 registers from 14 Aug 2026 to 10 Oct 2026.

  • 10 Oct 2026 register
    Added to the register

Also at Dalry 400kV Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO