Beauly 02 BESS
- Connection date
- 31 Dec 2028
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 100 MW
- Connected now
- 0 MW
- Still to connect
- 100 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-003731
- In the register since
- June 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Oct 2026 registerConnection date moved from 31 Oct 2028 to 31 Dec 2028 (+2 months)
- 10 Oct 2026 registerConnection date moved from 31 Dec 2028 to 31 Oct 2028 (−2 months)
- 10 Oct 2026 registerMarked as Gate 1
- 24 Jul 2026 registerTransmission owner changed from SPT to SHET
- 14 Jul 2026 registerConnection point changed from Beauly GSP to BEAULY 02 BESS 132kV SUBSTATION
- 14 Jul 2026 registerTransmission owner changed from SHET to SPT
- 29 Jul 2025 registerCustomer changed from Virmati Energy Ltd to FIELD BEAULY LTD
- 28 Feb 2025 registerCustomer changed from Field Devco Ltd to Virmati Energy Ltd
- 31 Jan 2025 registerCustomer changed from VIRMATI ENERGY LTD to Field Devco Ltd
- 29 Oct 2024 registerCustomer changed from Field Gaia Ltd to VIRMATI ENERGY LTD
- 31 May 2024 registerCustomer changed from VIRMATI ENERGY LTD to Field Gaia Ltd
- 30 Jun 2023 registerAdded to the register
Also at BEAULY 02 BESS 132kV SUBSTATION
Substation viewNo other projects in the register at this connection point.