ER BUR Energy
ER PROJECT DEVELOPMENT CO LIMITED at Burwell South 400kV Substation
- Connection date
- 28 Oct 2033
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003721
- In the register since
- January 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 12 Jun 2026 registerMarked as Gate 1
- 30 Jan 2024 registerAdded to the register
Also at Burwell South 400kV Substation
Substation view2 other projects, 507 MW still to connect at this substation in total. 200 MW is due to connect here before this project’s connection date of 28 Oct 2033.