Thornton BESS
REWE 9 LIMITED at North Humber Connection Node C 400kV Substation
- Connection date
- 30 Oct 2035
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003684
- In the register since
- October 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 17 Apr 2026 registerConnection point changed from Thornton 400kV Substation to North Humber Connection Node C 400kV Substation
- 17 Apr 2026 registerMarked as Gate 1
- 28 Feb 2025 registerConnection date moved from 31 Oct 2034 to 30 Oct 2035 (+12 months)
- 30 Jul 2024 registerCustomer changed from CSWE 9 LIMITED to REWE 9 LIMITED
- 31 Oct 2023 registerAdded to the register
Also at North Humber Connection Node C 400kV Substation
Substation viewNo other projects in the register at this connection point.