Darnall Road
- Connection date
- 30 Oct 2034
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted 2 Aug 2022
Sheffield, reference 22/01021/FUL · Source: REPD - Technology
- Storage
- Total capacity
- 40 MW
- Connected now
- 0 MW
- Still to connect
- 40 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Embedded
- Region
- England and Wales
- Project number
- PRO-003641
- In the register since
- December 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Sep 2024 registerConnection date moved from 31 Oct 2033 to 30 Oct 2034 (+12 months)
- 29 Dec 2023 registerAdded to the register
Also at West Melton GSP
Substation viewNo other projects in the register at this connection point.