Glennifer Road BESS
Drax BESS Neilston Limited at Glennifer Road BESS 132kV substation
- Connection date
- 31 Jul 2028 +9 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 150 MW
- Connected now
- 0 MW
- Still to connect
- 150 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-003600
- In the register since
- May 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Consents Approved
- 17 Jul 2026 registerConnection point changed from Neilston 132kV Substation to Glennifer Road BESS 132kV substation
- 17 Jul 2026 registerConnection date moved from 30 Oct 2027 to 31 Jul 2028 (+9 months)
- 17 Jul 2026 registerGiven a Gate 2 connection offer
- 6 Mar 2026 registerCustomer changed from GPC 1119 Ltd to Drax BESS Neilston Limited
- 19 Dec 2025 registerConnection point changed from Neilston 400/275/132kV to Neilston 132kV Substation
- 31 Jan 2025 registerConnection date moved from 30 Sep 2027 to 30 Oct 2027 (+1 month)
- 27 Sep 2024 registerRenamed from Gennifer Road BESS
- 27 Sep 2024 registerConnection point changed from Neilston 132kV Substation to Neilston 400/275/132kV
- 27 Aug 2024 registerRenamed from Thornlemuir Farm
- 30 May 2023 registerAdded to the register
Also at Glennifer Road BESS 132kV substation
Substation viewNo other projects in the register at this connection point.