- Connection date
- 26 May 2028
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 500 MW
- Connected now
- 0 MW
- Still to connect
- 500 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-003596
- In the register since
- June 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerCustomer changed from NEW ENERGY PARTNERSHIP LIMITED to Braston New Energy Limited
- 29 Jul 2025 registerConnection point changed from Ayr 275/33kV to Ayr Farm Collector Substation
- 24 Dec 2024 registerCapacity changed from 300 MW to 500 MW
- 24 Dec 2024 registerConnection date moved from 30 Aug 2030 to 26 May 2028 (−27 months)
- 27 Sep 2024 registerSubstation name updated in the register (from Ayr 275/33 kV Substation to Ayr 275/33kV)
- 28 Jul 2023 registerConnection date moved from 1 Apr 2027 to 30 Aug 2030 (+41 months)
- 30 Jun 2023 registerAdded to the register
Also at Ayr Farm Collector Substation
Substation viewNo other projects in the register at this connection point.