Craigneuk 250MW BESS
Apatura Project 23 Ltd at Craigneuk 250MW BESS 275kV Substation
- Connection date
- 31 Oct 2034
- Gate
- Not stated
- Status
- Scoping
- Technology
- Demand + Storage
- Total capacity
- 250 MW
- Connected now
- 0 MW
- Still to connect
- 250 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-003579
- In the register since
- November 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerCustomer changed from Apatura Battery Ltd to Apatura Project 23 Ltd
- 29 Jul 2025 registerConnection date moved from 31 Oct 2028 to 31 Oct 2034 (+72 months)
- 27 Jun 2025 registerConnection point changed from Newarthill Energy Park 275kV Substation to Craigneuk 250MW BESS 275kV Substation
- 27 Jun 2025 registerTechnology changed from Storage to Demand, Storage
- 28 Mar 2025 registerConnection date moved from 31 Aug 2028 to 31 Oct 2028 (+2 months)
- 28 Feb 2025 registerRenamed from Greenside BESS
- 28 Jun 2024 registerCustomer changed from GPC Battery Ltd to Apatura Battery Ltd
- 28 Nov 2023 registerAdded to the register
Also at Craigneuk 250MW BESS 275kV Substation
Substation viewNo other projects in the register at this connection point.