Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland

Motherwell 400MW BESS (Formerly Castlehill BESS)

SPV GPC 3 Ltd at Newarthill 275 kV Substation

Connection date
30 Apr 2035
Gate
Not stated
Status
Scoping
Technology
Demand + Storage
Total capacity
400 MW
Connected now
0 MW
Still to connect
400 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-003500
In the register since
January 2024

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 29 Jul 2025 register
    Customer changed from Apatura Battery Ltd to SPV GPC 3 Ltd
  • 30 May 2025 register
    Connection point changed from Castlehill BESS 400kV Substation to Newarthill 275 kV Substation
  • 30 May 2025 register
    Connection date moved from 31 Oct 2030 to 30 Apr 2035 (+54 months)
  • 30 May 2025 register
    Technology changed from Storage to Demand, Storage
  • 28 Feb 2025 register
    Connection point changed from Wishaw 275/132/33kV to Castlehill BESS 400kV Substation
  • 31 Jan 2025 register
    Renamed from Castlehill BESS
  • 29 Oct 2024 register
    Connection point changed from Wishaw 400/275/132/33kVx to Wishaw 275/132/33kV
  • 27 Sep 2024 register
    Connection point changed from Wishaw (SPD) GSP to Wishaw 400/275/132/33kVx
  • 28 Jun 2024 register
    Customer changed from GPC Battery Ltd to Apatura Battery Ltd
  • 30 Jan 2024 register
    Added to the register

Also at Newarthill 275 kV Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO