Bankend Rig III Wind Farm
WILSON RENEWABLES III LLP at Bankend Rig III 132kV Collector Substation
- Connection date
- 30 Apr 2030
- Gate
- Not stated
- Status
- Scoping
- Technology
- Onshore wind
- Total capacity
- 78 MW
- Connected now
- 0 MW
- Still to connect
- 78 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-003451
- In the register since
- March 2023
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerConnection point changed from Bankend Rig III Windfarm 132/33kV Substation to Bankend Rig III 132kV Collector Substation
- 31 Mar 2023 registerAdded to the register
Also at Bankend Rig III 132kV Collector Substation
Substation viewNo other projects in the register at this connection point.