GF Thornton Energy BESS
THORNTON ENERGY LTD at North Humber Connection Node A 400kV Substation
- Connection date
- 30 Oct 2035 +24 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Planning consent
- Granted 27 Feb 2026
East Riding of Yorkshire, reference 25/01685/STPLF · Source: REPD - Technology
- Storage
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003449
- In the register since
- February 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 31 Oct 2033 to 30 Oct 2035 (+24 months)
- 7 Apr 2026 registerConnection point changed from Thornton 400kV Substation to North Humber Connection Node A 400kV Substation
- 7 Apr 2026 registerMarked as Gate 1
- 13 Mar 2026 registerCustomer changed from GF THORNTON ENERGY LTD to THORNTON ENERGY LTD
- 30 Jul 2024 registerCustomer changed from GF THRONTON ENERGY LTD to GF THORNTON ENERGY LTD
- 27 Feb 2024 registerAdded to the register
Also at North Humber Connection Node A 400kV Substation
Substation view1 other project, 1 GW still to connect at this substation in total.