Gresham House Connagill BESS
ENERGYHUBDEVELOPMENTS LIMITED at New Connagill 275/132kV Substation
- Connection date
- 31 Oct 2031
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 170 MW
- Connected now
- 0 MW
- Still to connect
- 170 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-003434
- In the register since
- December 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 31 Jul 2026 registerMarked as Gate 1
- 13 Mar 2026 registerCustomer changed from Gresham House Devco Pipeline Limited to ENERGYHUBDEVELOPMENTS LIMITED
- 29 Aug 2025 registerConnection point changed from Connagill 132kV Substation to New Connagill 275/132kV Substation
- 27 Jun 2025 registerConnection point changed from Connagill 275kV Substation to Connagill 132kV Substation
- 27 Jun 2025 registerCapacity changed from 240 MW to 170 MW
- 27 Jun 2025 registerConnection date moved from 31 Oct 2030 to 31 Oct 2031 (+12 months)
- 29 Dec 2023 registerAdded to the register
Also at New Connagill 275/132kV Substation
Substation view1 other project, 220 MW still to connect at this substation in total.