- Connection date
- 31 Oct 2038
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 1,000 MW
- Connected now
- 0 MW
- Still to connect
- 1,000 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003410
- In the register since
- August 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 31 Jul 2026 registerConnection point changed from London West Connection Node B 400kV Substation to London North West Connection Node B 400kV Substation
- 21 Apr 2026 registerMarked as Gate 1
- 24 Dec 2024 registerConnection date moved from 31 Oct 2037 to 31 Oct 2038 (+12 months)
- 29 Oct 2024 registerConnection point changed from West Weybridge 400kV Substation to London West Connection Node B 400kV Substation
- 27 Feb 2024 registerCustomer changed from ORRÖN ENERGY DEVELOPMENT LIMITED to West Weybridge 10 Renewables Limited
- 29 Aug 2023 registerAdded to the register
Also at London North West Connection Node B 400kV Substation
Substation viewNo other projects in the register at this connection point.