- Connection date
- 31 Oct 2034
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Demand + Storage + Solar + Reactive compensation
- Total capacity
- 800 MW
- Connected now
- 0 MW
- Still to connect
- 800 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003275
- In the register since
- December 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Awaiting Consents
- 29 Oct 2024 registerConnection point changed from Scarning 400kV Substation to North Anglia Connection Node C 400kV Substation
- 29 Oct 2024 registerCapacity changed from 1,400 MW to 800 MW
- 29 Dec 2023 registerAdded to the register
Also at North Anglia Connection Node C 400kV Substation
Substation view2 other projects, 2.5 GW still to connect at this substation in total.