Projects / England and Wales
Connection date
31 Oct 2034
Gate
Not stated
Status
Awaiting consent
Technology
Demand + Storage + Solar + Reactive compensation
Total capacity
800 MW
Connected now
0 MW
Still to connect
800 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-003275
Tracked since
14 Aug 2026

Change history

Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.

  • 18 Sep 2026 register
    Status changed from Scoping to Awaiting consent

Also queued at North Anglia Connection Node C 400kV Substation

Substation view

2 other projects, 2.5 GW still to connect at this substation in total.