Grangemouth Hybrid BESS & Solar PV
TAGENERGY DEVELOPMENT UK LIMITED at Letham 400/275kV substation
- Connection date
- 30 Jun 2032
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 300 MW
- Connected now
- 0 MW
- Still to connect
- 300 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-003254
- In the register since
- January 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Oct 2026 registerConnection date moved from 30 Apr 2032 to 30 Jun 2032 (+2 months)
- 10 Oct 2026 registerConnection date moved from 30 Jun 2032 to 30 Apr 2032 (−2 months)
- 12 May 2026 registerMarked as Gate 1
- 29 Jul 2025 registerConnection point changed from Grangemouth 275/33kV to Letham 400/275kV substation
- 24 Dec 2024 registerConnection date moved from 31 Oct 2028 to 30 Jun 2032 (+44 months)
- 30 Jan 2024 registerAdded to the register
Also at Letham 400/275kV substation
Substation viewNo other projects in the register at this connection point.