- Connection date
- 30 Oct 2034
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003248
- In the register since
- November 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 24 Dec 2024 registerConnection date moved from 31 Oct 2035 to 30 Oct 2034 (−12 months)
- 30 Jul 2024 registerConnection point changed from Chesterfield GSP to Chesterfield 400kV Substation (Not yet constructed)
- 28 Nov 2023 registerAdded to the register
Also at Chesterfield 400kV Substation (Not yet constructed)
Substation view1 other project, 657 MW still to connect at this substation in total. 600 MW is due to connect here before this project’s connection date of 30 Oct 2034.