Elstree Energy Storage
ELSTREE BATTERY STORAGE LIMITED at Letchmore Heath 132kV Substation
- Connection date
- 31 Jul 2030 +10 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 170 MW
- Connected now
- 0 MW
- Still to connect
- 170 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003205
- In the register since
- February 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 1 Oct 2029 to 31 Jul 2030 (+10 months)
- 9 Jun 2026 registerConnection point changed from Elstree 132kV Substation to Letchmore Heath 132kV Substation
- 8 May 2026 registerMarked as Gate 1
- 29 Aug 2025 registerCustomer changed from BW ESS Development UK Limited to ELSTREE BATTERY STORAGE LIMITED
- 31 Jan 2025 registerCustomer changed from Penso Power Limited to BW ESS DEVELOPMENT UK LIMITED
- 31 Mar 2023 registerCapacity changed from 200 MW to 170 MW
- 28 Feb 2023 registerAdded to the register
Also at Letchmore Heath 132kV Substation
Substation viewNo other projects in the register at this connection point.