Elmya Hunterston
ELMYA RPC UK HUNTERSTON LIMITED at KEPPEN BURN 400KV SUBSTATION
- Connection date
- 25 Oct 2030
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-003182
- In the register since
- March 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerAdded to the register
- 25 Aug 2026 registerLeft the register (400 MW from 25 Oct 2030)
- 11 Aug 2026 registerConnection point changed from Hunterston 400/132kV to KEPPEN BURN 400KV SUBSTATION
- 19 Jun 2026 registerMarked as Gate 1
- 24 Dec 2024 registerConnection date moved from 9 Oct 2029 to 25 Oct 2030 (+13 months)
- 27 Sep 2024 registerConnection point changed from Hunterston 400kV Substation to Hunterston 400/132kV
- 30 Jan 2024 registerCustomer changed from ELMYA ENERGY UK 2 LIMITED to ELMYA RPC UK HUNTERSTON LIMITED
- 30 Jun 2023 registerStatus changed from Scoping to Awaiting Consents
- 31 Mar 2023 registerAdded to the register
Also at KEPPEN BURN 400KV SUBSTATION
Substation viewNo other projects in the register at this connection point.