Solomons Farm BESS
Solomons BESS Ltd at North Kent Connection Node B 132kV Substation
- Connection date
- 31 Oct 2033 +36 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 240 MW
- Connected now
- 0 MW
- Still to connect
- 240 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Embedded
- Region
- England and Wales
- Project number
- PRO-003181
- In the register since
- February 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 31 Oct 2030 to 31 Oct 2033 (+36 months)
- 10 Oct 2026 registerMarked as Gate 1
- 29 Jul 2025 registerCustomer changed from Bluestone Energy Ltd to Solomons BESS Ltd
- 29 Jul 2025 registerConnection point changed from Kingsnorth GSP to North Kent Connection Node B 132kV Substation
- 27 Feb 2024 registerAdded to the register
Also at North Kent Connection Node B 132kV Substation
Substation viewNo other projects in the register at this connection point.