Beddington 1 BESS
Bluestone Beddington 1 Ltd at London South Connection Node A 132kV Substation
- Connection date
- 31 Oct 2037
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 240 MW
- Connected now
- 0 MW
- Still to connect
- 240 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Embedded
- Region
- England and Wales
- Project number
- PRO-003170
- In the register since
- February 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Oct 2026 registerConnection date moved from 30 Oct 2037 to 31 Oct 2037 (1 day later)
- 10 Oct 2026 registerConnection date moved from 31 Oct 2037 to 30 Oct 2037 (1 day earlier)
- 5 Jun 2026 registerMarked as Gate 1
- 27 Jun 2025 registerCustomer changed from Bluestone Energy Ltd to Bluestone Beddington 1 LTD
- 28 Feb 2025 registerConnection date moved from 31 Oct 2028 to 31 Oct 2037 (+108 months)
- 31 Jan 2025 registerConnection point changed from Beddington 132kV Substation to London South Connection Node A 132kV Substation
- 27 Feb 2024 registerAdded to the register
Also at London South Connection Node A 132kV Substation
Substation view1 other project, 480 MW still to connect at this substation in total.