Helen Street BESS
- Connection date
- 28 Jun 2028
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Embedded
- Region
- South Scotland
- Project number
- PRO-003168
- In the register since
- October 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 May 2025 registerConnection date moved from 30 Jun 2026 to 28 Jun 2028 (+24 months)
- 27 Sep 2024 registerSubstation name updated in the register (from Govan GSP to Govan 132/33kV)
- 31 Oct 2023 registerAdded to the register
Also at Govan 132/33kV
Substation viewNo other projects in the register at this connection point.