Wright Street BESS
- Connection date
- 31 Oct 2025 +3 months since 9 Dec
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Refused 28 May 2024
Renfrewshire, reference 24/0153/PP · Source: REPD - Technology
- Storage
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Embedded
- Region
- South Scotland
- Project number
- PRO-003083
- In the register since
- May 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 24 Jul 2026 registerConnection date moved from 16 Jul 2025 to 31 Oct 2025 (+3 months)
- 27 Sep 2024 registerSubstation name updated in the register (from Braehead Park GSP to Braehead Park 132/33kV)
- 30 May 2023 registerAdded to the register
Also at Braehead Park 132/33kV
Substation view1 other project, 99.9 MW still to connect at this substation in total.