Riccarton
- Connection date
- 13 Apr 2029
- Gate
- Gate 1
- Status
- Scoping
- Planning consent
- Application submitted 26 Mar 2025
Scottish Government (S36), reference ECU00005144 · Source: REPD - Technology
- Storage + Solar
- Total capacity
- 150 MW
- Connected now
- 0 MW
- Still to connect
- 150 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-003066
- In the register since
- February 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 19 Jun 2026 registerMarked as Gate 1
- 28 Mar 2025 registerConnection point changed from Currie 132/11kV to Currie 275/132kV
- 29 Oct 2024 registerConnection point changed from Currie 275/132/11kV to Currie 132/11kV
- 27 Sep 2024 registerSubstation name updated in the register (from Currie GSP to Currie 275/132/11kV)
- 27 Feb 2024 registerAdded to the register
Also at Currie 275/132kV
Substation viewNo other projects in the register at this connection point.