MALTBY DEV.
- Connection date
- 31 Oct 2034
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003064
- In the register since
- July 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 24 Apr 2026 registerMarked as Gate 1
- 24 Dec 2024 registerConnection date moved from 31 Oct 2033 to 31 Oct 2034 (+12 months)
- 30 Jul 2024 registerAdded to the register
Also at Thurcroft 275kV Substation
Substation view1 other project, 500 MW still to connect at this substation in total. 99.9 MW is due to connect here before this project’s connection date of 31 Oct 2034.