Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland

Saltcoats NEP BESS Facility

Rashley New Energy Limited at Saltcoats 132/33kV

Connection date
31 Oct 2029
Gate
Not stated
Status
Awaiting Consents
Technology
Storage
Total capacity
100 MW
Connected now
0 MW
Still to connect
100 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-002813
In the register since
January 2024

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 18 Sep 2026 register
    Status changed from Scoping to Awaiting Consents
  • 29 Aug 2025 register
    Customer changed from NEW ENERGY PARTNERSHIP LIMITED to Rashley New Energy Limited
  • 27 Sep 2024 register
    Connection point changed from Saltcoats 132kV Substation to Saltcoats 132/33kV
  • 27 Aug 2024 register
    Connection date moved from 28 Jun 2030 to 31 Oct 2029 (−8 months)
  • 30 Jan 2024 register
    Added to the register

Also at Saltcoats 132/33kV

Substation view

1 other project, 130 MW still to connect at this substation in total. 30 MW is due to connect here before this project’s connection date of 31 Oct 2029.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO