Peterhead PV and BESS Station
- Connection date
- 31 Oct 2033
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Storage + Solar
- Total capacity
- 480 MW
- Connected now
- 0 MW
- Still to connect
- 480 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-002775
- In the register since
- September 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 31 Oct 2023 registerConnection point changed from Peterhead 400/275/33kV Substation to New Deer 2 400kV Substation
- 29 Sep 2023 registerAdded to the register
Also at New Deer 2 400kV Substation
Substation view3 other projects, 1.7 GW still to connect at this substation in total.