Rigifa BESS
- Connection date
- 12 Dec 2029
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-002758
- In the register since
- August 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 17 Apr 2026 registerMarked as Gate 1
- 29 Jul 2025 registerCustomer changed from FIELD DEVCO LTD to FIELD RIGIFA LIMITED
- 29 Apr 2025 registerCustomer changed from FIELD RIGIFA LIMITED to FIELD DEVCO LTD
- 29 Apr 2025 registerConnection date moved from 31 Jul 2031 to 12 Dec 2029 (−20 months)
- 28 Feb 2025 registerCustomer changed from FIELD DEVCO LTD to FIELD RIGIFA LIMITED
- 29 Aug 2023 registerAdded to the register
Also at Gills Bay 132kV
Substation view1 other project, 299 MW still to connect at this substation in total.