Enderby Farm
548 UK INVESTMENT HOLDINGS LIMITED at Earl Shilton 400kV Substation
- Connection date
- 31 Oct 2034
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002682
- Tracked since
- 10 Oct 2026
Change history
Every change to this project across 14 registers from 14 Aug 2026 to 10 Oct 2026.
- 10 Oct 2026 registerAdded to the register
Also at Earl Shilton 400kV Substation
Substation view2 other projects, 1.1 GW still to connect at this substation in total. 250 MW is due to connect here before this project’s connection date of 31 Oct 2034.