Grendon High Impact Green Energy Hub (HIGEH) 1
- Connection date
- 31 Oct 2033
- Gate
- Gate 1
- Status
- Awaiting Consents
- Technology
- Storage + Nuclear + Solar + Reactive compensation + Onshore wind
- Total capacity
- 1,000 MW
- Connected now
- 0 MW
- Still to connect
- 1,000 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002651
- In the register since
- July 2023
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 6 Mar 2026 registerMarked as Gate 1
- 24 Feb 2026 registerConnection point changed from Grendon 400kV Substation to LAVENDON 400KV SUBSTATION
- 28 Jun 2024 registerStatus changed from Scoping to Awaiting Consents
- 27 Feb 2024 registerStatus changed from Awaiting Consents to Scoping
- 29 Sep 2023 registerConnection point changed from Lavendon 400kV Substation to Grendon 400kV Substation
- 29 Aug 2023 registerConnection point changed from New Grendon Area Substation to Lavendon 400kV Substation
- 28 Jul 2023 registerAdded to the register
Also at LAVENDON 400KV SUBSTATION
Substation viewNo other projects in the register at this connection point.