Didcot High Impact Green Energy Hub (HIGEH) 1
- Connection date
- 31 Oct 2037
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Gas (CCGT) + Storage + Solar + Onshore wind
- Total capacity
- 1,000 MW
- Connected now
- 0 MW
- Still to connect
- 1,000 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002649
- In the register since
- May 2023
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 15 May 2026 registerMarked as Gate 1
- 21 Nov 2025 registerConnection point changed from Didcot 400kV Substation to Appleford 400kV
- 29 Jul 2025 registerTechnology changed from Storage, Nuclear, Solar, Reactive compensation, Onshore wind to Gas (CCGT), Storage, Solar, Onshore wind
- 27 Feb 2024 registerStatus changed from Awaiting Consents to Scoping
- 30 May 2023 registerAdded to the register
Also at APPLEFORD 400kV SUBSTATION
Substation view2 other projects, 1.9 GW still to connect at this substation in total.