Ardleigh Solar & BESS
- Connection date
- 31 Oct 2032
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 600 MW
- Connected now
- 0 MW
- Still to connect
- 600 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002644
- In the register since
- September 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Sep 2023 registerAdded to the register
Also at Hadleigh 400kV Substation
Substation viewNo other projects in the register at this connection point.