Smeaton BESS
- Connection date
- 31 Jul 2028 +10 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted 29 Aug 2024
Scottish Government (S36), reference ECU00004783 · Source: REPD - Technology
- Storage
- Total capacity
- 228 MW
- Connected now
- 0 MW
- Still to connect
- 228 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-002635
- In the register since
- July 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 1 Oct 2026 registerConnection date moved from 30 Sep 2027 to 31 Jul 2028 (+10 months)
- 1 Oct 2026 registerStatus changed from Scoping to Consents Approved
- 1 Oct 2026 registerGiven a Gate 2 connection offer
- 18 Sep 2026 registerConnection point changed from Smeaton 400/275kV to Smeaton 400kV
- 27 Jun 2025 registerConnection date moved from 23 Jun 2028 to 30 Sep 2027 (−9 months)
- 27 Sep 2024 registerConnection point changed from Smeaton 400kV to Smeaton 400/275kV
- 28 Jul 2023 registerAdded to the register
Also at Smeaton 400kV
Substation viewNo other projects in the register at this connection point.