Loch Fearna Pumped Storage
FEARNA PSH LIMITED at Loch Fearna Pumped Storage 400/18kV Substation
- Connection date
- 28 Oct 2032
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Pumped storage
- Total capacity
- 300 MW
- Connected now
- 0 MW
- Still to connect
- 300 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-002569
- In the register since
- November 2022
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Awaiting Consents
- 29 Aug 2025 registerConnection point changed from Loch Fearna Pumped Storage 132/18kV to Loch Fearna Pumped Storage 400/18kV Substation
- 29 Oct 2024 registerConnection date moved from 31 Oct 2029 to 28 Oct 2032 (+36 months)
- 31 May 2024 registerCustomer changed from GILKES ENERGY LIMITED to FEARNA PSH LIMITED
- 28 Apr 2023 registerRenamed from Loch Fearna Pump Storage
- 29 Nov 2022 registerAdded to the register
Also at Loch Fearna Pumped Storage 400/18kV Substation
Substation viewNo other projects in the register at this connection point.