Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland

Newarthill Energy Park

Dalzell (Newarthill) Ltd at Newarthill Energy Park 275kV Substation

Connection date
31 Oct 2029 +24 months since 9 Dec
Gate
Gate 2
Status
Scoping
Planning consent
Granted 4 Feb 2025
Scottish Government (S36), reference ECU00004953 · Source: REPD
Technology
Storage
Total capacity
300 MW
Connected now
0 MW
Still to connect
300 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-002532
In the register since
February 2023

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 18 Sep 2026 register
    Status changed from Consents Approved to Scoping
  • 25 Aug 2026 register
    Status changed from Awaiting Consents to Consents Approved
  • 24 Jul 2026 register
    Customer changed from Geocore (Newarthill) Ltd to Dalzell (Newarthill) Ltd
  • 14 Jul 2026 register
    Capacity changed from 300 MW to 300 MW
  • 10 Jul 2026 register
    Connection date moved from 28 Oct 2029 to 31 Oct 2029 (3 days later)
  • 3 Jul 2026 register
    Capacity changed from 300 MW to 300 MW
  • 3 Jul 2026 register
    Connection date moved from 28 Oct 2027 to 28 Oct 2029 (+24 months)
  • 3 Jul 2026 register
    Given a Gate 2 connection offer
  • 28 Mar 2025 register
    Status changed from Scoping to Awaiting Consents
  • 29 Oct 2024 register
    Capacity changed from 250 MW to 300 MW
  • 27 Feb 2024 register
    Customer changed from Geocore Ltd to Geocore (Newarthill) Ltd
  • 28 Nov 2023 register
    Technology changed from Demand, Storage to Storage
  • 28 Feb 2023 register
    Added to the register

Also at Newarthill Energy Park 275kV Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning consent

The planning decision or stage for this project, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition, with the planning authority and its reference. QueueWatch matched the project to that record. NESO’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.