Newarthill Energy Park
Dalzell (Newarthill) Ltd at Newarthill Energy Park 275kV Substation
- Connection date
- 31 Oct 2029 +24 months since 9 Dec
- Gate
- Gate 2
- Status
- Scoping
- Planning consent
- Granted 4 Feb 2025
Scottish Government (S36), reference ECU00004953 · Source: REPD - Technology
- Storage
- Total capacity
- 300 MW
- Connected now
- 0 MW
- Still to connect
- 300 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-002532
- In the register since
- February 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Consents Approved to Scoping
- 25 Aug 2026 registerStatus changed from Awaiting Consents to Consents Approved
- 24 Jul 2026 registerCustomer changed from Geocore (Newarthill) Ltd to Dalzell (Newarthill) Ltd
- 14 Jul 2026 registerCapacity changed from 300 MW to 300 MW
- 10 Jul 2026 registerConnection date moved from 28 Oct 2029 to 31 Oct 2029 (3 days later)
- 3 Jul 2026 registerCapacity changed from 300 MW to 300 MW
- 3 Jul 2026 registerConnection date moved from 28 Oct 2027 to 28 Oct 2029 (+24 months)
- 3 Jul 2026 registerGiven a Gate 2 connection offer
- 28 Mar 2025 registerStatus changed from Scoping to Awaiting Consents
- 29 Oct 2024 registerCapacity changed from 250 MW to 300 MW
- 27 Feb 2024 registerCustomer changed from Geocore Ltd to Geocore (Newarthill) Ltd
- 28 Nov 2023 registerTechnology changed from Demand, Storage to Storage
- 28 Feb 2023 registerAdded to the register
Also at Newarthill Energy Park 275kV Substation
Substation viewNo other projects in the register at this connection point.