Learielaw Energy Storage
Learielaw Energy Storage Limited at Learlielaw Energy Storage 132kV Substation
- Connection date
- 31 Oct 2028
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted 19 May 2025
Scottish Government (S36), reference ECU00004983 · Source: REPD - Technology
- Storage
- Total capacity
- 100 MW
- Connected now
- 0 MW
- Still to connect
- 100 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-002531
- In the register since
- May 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 19 Dec 2025 registerConnection point changed from Broxburn 132/33kV to Learlielaw Energy Storage 132kV Substation
- 29 Aug 2025 registerTechnology changed from Demand, Storage to Storage
- 27 Sep 2024 registerSubstation name updated in the register (from Broxburn GSP to Broxburn 132/33kV)
- 30 May 2023 registerAdded to the register
Also at Learlielaw Energy Storage 132kV Substation
Substation viewNo other projects in the register at this connection point.