Dolphingstone Farm
- Connection date
- 31 Oct 2028
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted 4 Jul 2025
Scottish Government (S36), reference ECU00004969 · Source: REPD - Technology
- Storage
- Total capacity
- 63 MW
- Connected now
- 0 MW
- Still to connect
- 63 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Embedded
- Region
- South Scotland
- Project number
- PRO-002451
- In the register since
- April 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Consents Approved
- 10 Jul 2026 registerCustomer changed from BROCKWELL STORAGE & SOLAR LIMITED to BSSL EAST LOTHIAN 1 LTD
- 19 Jun 2026 registerSubstation name updated in the register (from Cockenzie 275/33kV to Cockenzie 275/33kV Substation)
- 19 Jun 2026 registerGiven a Gate 2 connection offer
- 28 Feb 2025 registerConnection date moved from 30 Apr 2025 to 31 Oct 2028 (+42 months)
- 29 Oct 2024 registerSubstation name updated in the register (from Cockenzie GSP to Cockenzie 275/33kV)
- 28 Jun 2024 registerCustomer changed from RNA-ENERGY LTD to BROCKWELL STORAGE & SOLAR LIMITED
- 28 Apr 2023 registerAdded to the register
Also at Cockenzie 275/33kV Substation
Substation viewNo other projects in the register at this connection point.