Craig Nab Wind Energy Hub
Craig Nab Wind Energy Hub Limited at Ladyburn 132kV Substation
- Connection date
- 29 Aug 2031
- Gate
- Gate 1
- Status
- Scoping
- Planning consent
- Application submitted 20 Dec 2024
Dumfries and Galloway, reference 24/2545/FUL · Source: REPD - Technology
- Storage + Onshore wind
- Total capacity
- 36 MW
- Connected now
- 0 MW
- Still to connect
- 36 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Embedded
- Region
- South Scotland
- Project number
- PRO-002450
- In the register since
- June 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 28 Aug 2026 registerMarked as Gate 1
- 30 May 2025 registerConnection point changed from Glenluce 132/33kV Substation to Ladyburn 132kV Substation
- 30 May 2025 registerConnection date moved from 30 Jun 2028 to 29 Aug 2031 (+38 months)
- 30 Jun 2023 registerAdded to the register
Also at Ladyburn 132kV Substation
Substation view1 other project, 206 MW still to connect at this substation in total.