Dorenell Windfarm Extension
DORENELL WINDFARM EXTENSION LIMITED at Dorenell Extension Wind Farm 400kV Substation
- Connection date
- 31 Oct 2033
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Onshore wind
- Total capacity
- 610 MW
- Connected now
- 0 MW
- Still to connect
- 610 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-002415
- In the register since
- April 2023
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 1 May 2026 registerMarked as Gate 1
- 24 Apr 2026 registerConnection point changed from Blackhillock 400kV Substation to Dorenell Extension Wind Farm 400kV Substation
- 28 Apr 2023 registerAdded to the register
Also at Dorenell Extension Wind Farm 400kV Substation
Substation viewNo other projects in the register at this connection point.