Scaraben Offshore Wind Farm
SCARABEN OFFSHORE WIND FARM LIMITED at Longside 132kV Substation
- Connection date
- 31 Oct 2033
- Gate
- Not stated
- Status
- Scoping
- Technology
- Offshore wind
- Total capacity
- 100 MW
- Connected now
- 0 MW
- Still to connect
- 100 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-002401
- In the register since
- November 2022
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerCustomer changed from BLUEFLOAT ENERGY UK HOLDINGS LIMITED to SCARABEN OFFSHORE WIND FARM LIMITED
- 29 Jul 2025 registerConnection point changed from Scaraben 132kV Offshore Substation to Longside 132kV Substation
- 29 Aug 2023 registerConnection point changed from New Deer 2 400kV Substation to Scaraben 132kV Offshore Substation
- 23 Dec 2022 registerConnection point changed from Scaraben 132kV Offshore Substation to New Deer 2 400kV Substation
- 29 Nov 2022 registerAdded to the register
Also at Longside 132kV Substation
Substation view1 other project, 200 MW still to connect at this substation in total.