Drumore Farm
Drumore Battery Storage Limited at Alness 2 275/33 kV GSP Substation
- Connection date
- 31 Oct 2030
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted 10 Dec 2024
Highland, reference 23/02840/FUL · Source: REPD - Technology
- Storage
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-002397
- In the register since
- October 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 31 Oct 2025 registerTransmission owner changed from SPT to SHET
- 29 Aug 2025 registerCustomer changed from Fig Power Limited to Drumore Battery Storage Limited
- 29 Aug 2025 registerTransmission owner changed from SHET to SPT
- 31 May 2024 registerAdded to the register
- 26 Apr 2024 registerLeft the register (49.9 MW from 31 Oct 2030)
- 31 Oct 2023 registerAdded to the register
Also at Alness 2 275/33 kV GSP Substation
Substation view1 other project, 94.9 MW still to connect at this substation in total.