Tollgate 49.5MW BESS
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Planning consent
- Granted 22 Jan 2019
Welwyn Hatfield, reference 6/2017/2340/FULL · Source: REPD - Technology
- Storage
- Total capacity
- 49.5 MW
- Connected now
- 49.5 MW
- Still to connect
- 0 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Embedded
- Region
- England and Wales
- Project number
- PRO-002372
- In the register since
- September 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 31 Oct 2025 registerCapacity changed from 49.5 MW to 0 MW
- 31 Oct 2025 registerConnection date removed (was 31 Jan 2023)
- 29 Jul 2025 register49.5 MW now connected
- 29 Jul 2025 registerCapacity changed from 49.5 MW to 99 MW
- 30 May 2025 registerStatus changed from Consents Approved to Built
- 23 Dec 2022 registerConnection point changed from Elstree 132kV to Hatfield 33kV Substation
- 28 Oct 2022 registerConnection point changed from HATFIELD 33kV to Elstree 132kV
- 30 Sep 2022 registerAdded to the register
Also at Hatfield 33kV Substation
Substation viewNo other projects in the register at this connection point.