Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / North Scotland

Rothienorman 50MW BESS

ROTHIENORMAN FLEXPOWER LTD at Rothienorman 400/33kV Substation

Connection date
31 Jul 2027 +33 months since 9 Dec
Gate
Gate 2
Status
Consents Approved
Technology
Storage
Total capacity
50 MW
Connected now
0 MW
Still to connect
50 MW
Transmission owner
SSEN Transmission (SHET)
Agreement type
Embedded
Region
North Scotland
Project number
PRO-002300
In the register since
September 2022

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 18 Sep 2026 register
    Status changed from Scoping to Consents Approved
  • 14 Jul 2026 register
    Connection point changed from Rothienorman GSP to Rothienorman 400/33kV Substation
  • 14 Jul 2026 register
    Connection date moved from 31 Oct 2024 to 31 Jul 2027 (+33 months)
  • 14 Jul 2026 register
    Given a Gate 2 connection offer
  • 10 Jul 2026 register
    Customer changed from EQUINOR NEW ENERGY LIMITED to ROTHIENORMAN FLEXPOWER LTD
  • 26 Jun 2026 register
    Customer changed from ROTHIENORMAN FLEXPOWER LTD to EQUINOR NEW ENERGY LIMITED
  • 29 Jul 2025 register
    Customer changed from BLACKFORD RENEWABLES LTD to ROTHIENORMAN FLEXPOWER LTD
  • 27 Jun 2025 register
    Customer changed from Rothienorman Flexpower A Ltd to BLACKFORD RENEWABLES LTD
  • 27 Sep 2024 register
    Customer changed from ROTHIENORMAN FLEXPOWER LTD to Rothienorman Flexpower A Ltd
  • 31 Jan 2023 register
    Renamed from Rothienorman 50MW BESS (DNO)
  • 31 Jan 2023 register
    Customer changed from SCOTTISH HYDRO ELECTRIC POWER DISTRIBUTION PLC to ROTHIENORMAN FLEXPOWER LTD
  • 23 Dec 2022 register
    Renamed from Rothienorman 50MW BESS
  • 23 Dec 2022 register
    Customer changed from ROTHIENORMAN FLEXPOWER LTD to SCOTTISH HYDRO ELECTRIC POWER DISTRIBUTION PLC
  • 29 Nov 2022 register
    Added to the register
  • 28 Oct 2022 register
    Left the register (50 MW from 31 Oct 2024)
  • 30 Sep 2022 register
    Added to the register

Also at Rothienorman 400/33kV Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO